Featured Project Archives - Irby Construction Company Going the extra mile Wed, 30 Mar 2022 16:50:48 +0000 en-US hourly 1 https://wordpress.org/?v=6.8.3 Corbett-Sugar-Quarry 500kV Transmission Line Construction Project https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/ https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/#respond Tue, 12 Jun 2018 16:32:47 +0000 https://www.irbyconstruction.com/project/marshall-ford-to-lago-vista-copy/ The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>

Corbett-Sugar-Quarry 500kV Transmission Line Construction Project

Type: Transmission
Scope: Constructed 68.3 miles of 500kV transmission line including 15 miles of construction through Everglade canal waterways.
Location: South East Florida

Client: NextEra Energy Resources

NextEra Energy Resources (a parent company of FPL) is a wholesale electricity supplier with a portfolio of facilities totaling more than 21,000MW of electric generating capacity in the United States and Canada. In January 2018, NextEra contracted Irby to construct 68.3 miles of 500kV transmission line (single circuit, triple bundled) between Palm Beach and Miami-Dade counties (Corbett and Sugar substations to Quarry substation) in support of a critical tie-in for the NextEra’s Florida grid.

The Irby scope includes site survey, clearing, construction of access roads and pads, pier foundations and anchor pile installation, and setting steel structure and deadends with approximately 15 miles of the construction right of way transversing protected Everglade canal waterways.

In observance of the projects environmental requirements Irby crews adapted novel technical solutions including the use of barges, concrete pump lines, and amphibious equipment.

Start Date: January 2018
Completion Date: May 2019

 

If you would like to request information on this project or submit a request for bid, click here. 

 

The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>
https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/feed/ 0
Marshall Ford-Lago Vista 138kV Transmission Line Construction Project https://www.irbyconstruction.com/project/marshall-ford-lago-vista-138kv-transmission-line-construction-project/ Thu, 20 Jul 2017 22:50:05 +0000 https://www.irbyconstruction.com/project/sharyland-brown-to-grady-138kv-transmission-line-copy/ The post Marshall Ford-Lago Vista 138kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>

Marshall Ford-Lago Vista 138kV Transmission Line Construction Project

Type: Transmission, Water Crossing
Scope: Performed a 14.5 mile 138kV transmission line upgrade including a 1.3 mile crossing over Lake Travis.
Location: Austin, Texas

Client: Lower Colorado River Authority

In March 2016, Irby Construction was contracted by the Lower Colorado River Authority (“LCRA”) to perform the Marshall Ford to Lago Vista 138kV Transmission Line Construction Project. The project scope included the replacement of a 1.3 mile transmission line across Lake Travis plus the upgrade of an existing 14.5 mile transmission line (69kV to 138kV).

Irby Construction successfully completed this project in April of 2016 to schedule and budget.

To learn more about this project, click here.

Start Date: March 2016
Completion Date: April 2016

 

If you would like to request information on this project or submit a request for bid, click here. 

 

The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>
https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/feed/ 0
Eastern Alberta 500kV Transmission Line Construction Project https://www.irbyconstruction.com/project/eastern-alberta-500kv-transmission-line-construction-project/ Fri, 14 Jul 2017 20:28:01 +0000 https://www.irbyconstruction.com/project/entergy-ponderosa-to-grimes-230kv-transmission-line-copy/ The post Eastern Alberta 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>

Eastern Alberta 500kV Transmission Line Construction Project

Type: Transmission
Scope: Performed a 100 mile 500kV DC line transmission line construction project.
Location: Alberta, Canada

Client: Alberta Transmission Company

The Eastern Alberta Transmission Line is a 300 mile 500kV overhead transmission line interconnecting the Newell HVDC static inverter plant near Brooks, Alberta with the Heathfield static inverter plant near Gibbons, Alberta.

Owned by ATCO Electric, a subsidiary of Alberta Transmission Company (“ATCO”), the ~$1.3B project further strengthens ATCO’s capability to transmit and distribute electricity to its 227,000+ customers in north and east-central Alberta, the Yukon, and the North West Territories.

Subcontracted via Quanta Services affiliate Valard Construction (Irby and Valard are both Quanta Services subsidiaries (PWR:NYSE)), Irby performed 100 miles of stringing through two sub-zero Canadian winter seasons to energize the project on time and to budget in December 2015.

To learn more about this project, click here.

Start date: August 2013
Completion date: February 2015

 

If you would like to request information on this project or submit a request for bid, click here. 

 

The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>
https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/feed/ 0
Brown-Grady 138kV Transmission Line Rebuild Project https://www.irbyconstruction.com/project/brown-grady-138kv-transmission-line-rebuild-project/ Fri, 07 Jul 2017 18:48:02 +0000 https://www.irbyconstruction.com/project/entergy-ponderosa-to-grimes-230kv-transmission-line-copy/ The post Brown-Grady 138kV Transmission Line Rebuild Project appeared first on Irby Construction Company.

]]>

Brown-Grady 138kV Transmission Line Rebuild Project

Type: Transmission
Scope: Performed a 20.2 mile 138kV transmission line rebuild project.
Location: Big Spring, Texas

Client: Sharyland Utilities

Sharyland Utilities (“Sharyland”) is a Texas-based electric transmission utility providing wholesale energy within the Texas Interconnection (~24 million customers) as regulated by the Electric Reliability Council of Texas. In April 2016, Sharyland contracted Irby to rebuild 20.2 miles of 138kV transmission line near Martin County, West Texas.

As subcontractor to McCord Engineering (Sharyland’s nominated engineering firm), Irby’s scope included the tear-down and reconstruction of the existing 138kV transmission line, including concrete and steel poles, between Grady and Brown Substations. Five OPGW splice cans were installed along the route and construction also included four highway crossings.

The project was completed on time, to schedule, and with zero lost-time incidents in October 2016.

Start Date: April 2016
Completion Date: October 2016

 

If you would like to request information on this project or submit a request for bid, click here. 

 

The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>
https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/feed/ 0
Ponderosa-Grimes 230kV Transmission Line Construction Project https://www.irbyconstruction.com/project/ponderosa-grimes-230kv-transmission-line-construction-project/ Thu, 06 Apr 2017 21:07:15 +0000 https://www.irbyconstruction.com/?post_type=project&p=9187 The post Ponderosa-Grimes 230kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>

Ponderosa-Grimes 230kV Transmission Line Construction Project

Type: Transmission
Scope: Constructed 40 miles of 230kV transmission line including steel and concrete poles.
Location: Montgomery, Texas

Client: Entergy Corporation

Entergy Texas (an Entergy Corporation subsidiary) provides power to over 450,000 customers in 27 Texas counties. In September 2015, Entergy contracted Irby affiliate company Dashiell Engineering (Irby and Dashiell are Quanta Services subsidiary companies (PWR:NYSE)) to construct 40 miles of 230kV transmission line including steel and concrete poles between Entergy’s Ponderosa and Grimes substations in southeast Texas.

Irby Construction contracted Auger Services to construct the foundations and Winco (also a Quanta Services subsidiary company) to pull lead line and help clip the shield wire via helicopter.

This project was successfully completed in April 2016.

Start Date: September 2015
Completion Date: April 2016

 

If you would like to request information on this project or submit a request for bid, click here. 

 

The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>
https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/feed/ 0
Lake Charles Transmission Line Construction Project https://www.irbyconstruction.com/project/lake-charles-transmission-line-construction-project/ Thu, 06 Apr 2017 20:46:40 +0000 https://www.irbyconstruction.com/project/aep-valliant-to-northwest-345kv-transmission-line-copy/ The post Lake Charles Transmission Line Construction Project appeared first on Irby Construction Company.

]]>

Lake Charles Transmission Line Construction Project

Type: Transmission
Scope: Rebuilt 15 miles of 230kV plus 6.8 miles of 500kV transmission lines.
Location: Lake Charles, Louisiana

Client: Entergy Corporation

Entergy Louisiana (an Entergy Corporation subsidiary) is a power provider serving over 1 million customers across 58 parishes in Louisiana. In October 2016, Entergy contracted Dashiell Engineering (a Quanta Services company (PWR:NYSE)) to reconstruct 15 miles of 230kV and 6.8 miles of 500kV transmission line near Lake Charles on a turn-key basis.

Irby (also a Quanta Services company) was subcontracted to Dashiell to rebuild the lines, including foundations, steel, and concrete poles. Irby was assisted by Auger Services for pole setting/foundations and WInco for helicopter wire operations. Irby also performed conductor stringing works (1 mile) across the Calcasieu River. The project was completed in February 2018 to schedule and without lost-time incident.

Start Date: October 2016
Completion Date: February 2018

 

If you would like to request information on this project or submit a request for bid, click here. 

 

The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>
https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/feed/ 0
Valliant-Northwest Texarkana 345kV Transmission Line Construction Project https://www.irbyconstruction.com/project/valliant-northwest-texarkana-345kv-transmission-line-construction-project/ https://www.irbyconstruction.com/project/valliant-northwest-texarkana-345kv-transmission-line-construction-project/#respond Thu, 03 Nov 2016 15:11:20 +0000 https://www.irbyconstruction.com/project/ctt-gray-to-allen-creek-345kv-transmission-line-copy/ The post Valliant-Northwest Texarkana 345kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>

Valliant-Northwest Texarkana 345kV Transmission Line Construction Project

Type: Transmission
Scope: Constructed 43.5 miles of 345kV transmission line in Northeast Texas.
Location: New Boston, Texas

Client: American Electric Power

In April 2016, Irby Construction was awarded the contract for the construction of the Valliant to Northwest Texarkana Transmission Line project for AEP Southwestern Electric Power Company and AEP Oklahoma Transmission Company.

The project consisted of the installation of 43.5 miles of 345kV single steel pole transmission line on anchor-bolted foundations. Irby was supported by Erickson Air Crane and Winco for helicopter pole erection work scopes (Irby and Winco are Quanta Services subsidiary companies (PWR:NYSE)). The project was completed on time and with zero lost time incidents in January 2017.

Start Date: April 2016
Completion Date: January 2017

 

If you would like to request information on this project or submit a request for bid, click here. 

 

The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>
https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/feed/ 0
Gray-Allen Creek 345kV Transmission Line Construction Project https://www.irbyconstruction.com/project/ctt-gray-allen-creek-345kv-transmission/ https://www.irbyconstruction.com/project/ctt-gray-allen-creek-345kv-transmission/#respond Thu, 03 Nov 2016 20:02:11 +0000 https://www.irbyconstruction.com/project/gtc-burnt-church-tradeport-115kv-copy/ The post Gray-Allen Creek 345kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>

Gray-Allen Creek 345kV Transmission Line Construction Project

Type: Renewables, Transmission
Scope: Constructed 25 miles of 345kV transmission line in support of a North Texas wind project.
Location: Pampa, Texas

Client: Cross Texas Transmission

Founded in 2008, Cross Texas Transmission (“CTT”) is a regulated transmission service provider providing energy to wholesale markets across Texas. The bulk of CTT’s capacity derives from its owned and operated network of transmission lines (>320 miles) which delivers wind power from the Texas Panhandle to its customers.

In January 2016, CTT contracted Irby to incorporate power from the Salt Fork Wind project in Gray and Donley Counties by constructing 25 miles of 345kV transmission line. The Irby work scope included the installation of steel structures, foundations, and wire operations. Irby was assisted by Aldridge Construction (direct embed drilling and structure setting), Winco Powerline (lead-in installation and diverters), and B&M Telecom (Fiber splicing). Both Irby and Winco Powerline are Quanta Services subsidiary companies (PWR:NYSE).

The project was completed in August 2016 to schedule and with zero lost-time incidents.

To learn more about this project watch this video.

Start Date: January 2016
Completion Date: August 2016

 

If you would like to request information on this project or submit a request for bid, click here. 

 

The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>
https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/feed/ 0
Burnt Church-Tradeport 115kV Transmission Line Construction Project https://www.irbyconstruction.com/project/burnt-church-tradeport-115kv-transmission-line-construction-project/ https://www.irbyconstruction.com/project/burnt-church-tradeport-115kv-transmission-line-construction-project/#respond Tue, 29 Sep 2015 00:30:52 +0000 https://www.irbyconstruction.com/brightspot/?post_type=project&p=6154 The post Burnt Church-Tradeport 115kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>

Burnt Church-Tradeport 115kV Transmission Line Construction Project

Type: Transmission
Scope: Performed a 12.2 mile 115kV transmission line construction project in an environmentally sensitive coastal salt marsh.
Location: Brunswick, Georgia

Client: Georgia Transmission Corporation

In 2013, Georgia Transmission Corporation (“GTC”) contracted Irby to construct a 12.2 mile 115kv transmission line south of Savannah, Georgia including a 4 mile section through a protected salt marsh.

In service of the Coastal Electric Cooperatives service area, the project connected two radial transmission systems (Burnt Church and Tradeport) in Bryan and Liberty counties. In observance of the projects environmental sensitivity, Irby adapted a construction solution whereby poles were set by an Erikson S-64 Aircrane helicopter to minimize the impact to marshland ecosystems.

Completed on time and within strict environmental parameters, the project exemplified Irby’s capability to plan and execute novel technical solutions to the highest standards of environmental best practice.

To see more on this project, watch the project video produced by Georgia Transmission.

Start Date: April 2013
Completion Date: December 2013

 

If you would like to request information on this project or submit a request for bid, click here. 

 

The post Corbett-Sugar-Quarry 500kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>
https://www.irbyconstruction.com/project/corbett-sugar-quarry-500kv-transmission-line-construction-project/feed/ 0
Ohio River Crossing 345kV Transmission Line Construction Project https://www.irbyconstruction.com/project/ohio-river-crossing-345kv-transmission-line-construction-project/ https://www.irbyconstruction.com/project/ohio-river-crossing-345kv-transmission-line-construction-project/#respond Mon, 28 Sep 2015 16:21:08 +0000 https://www.irbyconstruction.com/brightspot/?post_type=project&p=6122 The post Ohio River Crossing 345kV Transmission Line Construction Project appeared first on Irby Construction Company.

]]>

Ohio River Crossing 345kV Transmission Line Construction Project

Type: Transmission, Water Crossing
Scope: Constructed a 2.42 mile 345kV river crossing including two 420 ft lattice towers.
Location: Bedford, Kentucky
Client: Kentucky Utilities

Kentucky Utilities, a subsidiary of PPL Corporation, is an electric utility which serves over 500,000 individuals throughout Virginia and Kentucky. Between August and December 2008, Kentucky Utilities contracted Irby to perform a 2.42 mile 345kV double circuit line crossing of the Ohio River.

The work scope included structure and wire installation work scopes including two 420 foot lattice towers for the river crossing. With foundation support from Can-Fer (Irby and Can-Fer are Quanta Services subsidiary companies PWR:NYSE)), the project was completed, on-time, to budget, and without lost time incident.

Start Date: August 2008
Completion Date: December 2008

 

If you would like to request information on this project or submit a request for bid, click here. 

 